Provide electricity to 500 students in Belize

by Holy Cross Education Foundation
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize
Provide electricity to 500 students in Belize

Project Report | Jul 22, 2013
Solar Phase 2: Contract signed!

By John McHenry | Solar Renewable Energy Project Manager

Introduction to 8th grade graduation ceremony
Introduction to 8th grade graduation ceremony

As noted in our last project report dated about the 15th of April 2013, we still needed approximately $14K to complete Phase 2. Our target dates were 1) to complete all fund-raising for Phase 2 by July 1, 2013; (2) formally sign the procurement contract with Baker Renewable Energy over the summer; and (3) initiate a the procurement, shipping, and installation of the second 5KW array with an expected completion date of March or April of 2014. I am thrilled to report significant progress since that time. First, an external grant was successful and resulted in an award of $9000.00 toward the overall budget, and a second $1000 gift was also received externally. These additional funds were sufficient to allow the HCEF board to proceed to finalize and sign the contract with BRE for Phase 2.BRE has also stepped up to the plate by keeping costs low --- providing up to a $10K like-kind donation for travel, installation, and other ancillary expenses. Thank you Baker Renewable Energy: http://bakerrenewable.com. Formal signing took place on July 9th. As a result, I have reduced the amount needed through our GG partnership by $10,000 -- this will be reflected as of July 20: overall, this means that we now need approximately $4000 to complete all fund raising for Phase 2. We are nearing the finish line in terms of raising funds for this phase.

In addition to this good news, the Board met in late June as part of the school graduation. HCAS graduated 37 8th grade (Standard VI) students this year, all of whom passed the Belizean national high-school qualifying exam. This achievement ranked us second among the 25 or so Anglican primary schools in the nation in terms of academic achievement. Way to go teachers, students, and staff!! Due to continued need for additional classroom space near San Mateo, we have been asked by the local town officials to consider starting a high-school, and this is under consideration by the Board. I have attached a few graduation and Board meeting pictures associated with this year's activities. Again thank you so much for your continued interest and support!!

Students on stage for graduation
Students on stage for graduation
Award ceremony!
Award ceremony!
Computer learning lab powered mainly by solar
Computer learning lab powered mainly by solar
Rainwater collection tank-pump also solar powered
Rainwater collection tank-pump also solar powered
Project Manager John McHenry and friend
Project Manager John McHenry and friend
Share on Twitter Share on Facebook

About Project Reports

Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.

Sign up for updates

Organization Information

Holy Cross Education Foundation

Location: Eden Prairie, MN - USA
Website:
Facebook: Facebook Page
Project Leader:
John McHenry
Eden Prairie , MN United States

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence

Snorkeler
Our
Impact

Woman Holding a Gift Card
Give
Gift Cards

Young Girl with a Bicycle
GlobalGiving
Guarantee

Get incredible stories, promotions, and matching offers in your inbox

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.