Project Report | Nov 6, 2024
FINAL REPORT OF THE DRILLING PROJECT IN SAGBADAI

By GBELE-GUEWE Djobo Ousmane | COORDINATOR

Well drilling at the project site on August 29, 20
Well drilling at the project site on August 29, 20

I - FINAL TECHNIQUE REPORT OF THE DRILLING PROJECT IN SAGBADAÏ

INTRODUCTION

The project “Improving access to water for the Sagbadaï community in the Tchaoudjo prefecture” began with the awareness-raising stage of this community on August 1, 2024. It is implemented by the NGO CAV with the financial support of the COCHRAN Family based in the USA through GlobalGiving.

This report summarizes all the activities carried out within the framework of the said project.

The following activities were carried out during the implementation of the said project:

-       Raising awareness among the population about the project and setting up drilling sites ;

-       Carrying out geophysical studies;

-       Drilling wells;

-       Water pumping and analysis;

-       Construction of the drilling superstructure;

-       Installation of the mechanical pump;

-       Monitoring of project activities.

PROGRESS OF ACTIVITIES

1. Raising awareness among the population about the project and establishing drilling sites:

The awareness-raising took place on August 1, 2024 in favor of the Sagbadaï community with the participation of the project team including the Coordinator and the Accountant of the NGO, the Director of the drilling company and the quality controller

During this awareness-raising session, the beneficiaries were provided with information on their responsibilities to now take charge of the management and maintenance of the works to be built.

An area of at least a quarter of a hectare has been selected by the community for geophysical studies.

2. Geophysical studies:

Geophysical studies were carried out on August 27, 2024. These studies revealed the existence of abundant water tables at an average depth of approximately 60 meters and a maximum depth of 90 meters. The site has the following coordinates: Longitude: 1.063242°, Latitude: 9.075943° and Altitude: 356.22

3. Drilling, Development and Equipment of Drilling

The drilling works were successfully completed on August 29, 2024 on the chosen site.

4. Pumping and physicochemical and microbiological analyses of borehole water:

The pumping of the boreholes was carried out two (2) weeks after the drilling stage. It took place on September 12, 2024 and consisted of:

ü  Measure the flow rate of the borehole;

ü  Determine the variation in its production at different flow rates;

ü  Quantify aquifer characteristics, including permeability coefficient and water storage capacity.

At the end of the pumping, water samples were taken for physicochemical and bacteriological analyses at the laboratory, at the Regional Directorate of Hygiene and Sanitation. The analyses were carried out from September 12 to 17, 2024.

The results of the analyses were therefore deemed satisfactory and fully meet WHO (World Health Organization) standards.

5. Construction of the drilling superstructure:

The activities to be carried out from September 26, 2024 have begun with the construction work of the drilling carried out from October 5 to 10, 2024.

The superstructure is composed of the coping, the hedgehog slab, the anti-quag, the fence of the lost well, the channel and decanter, all made according to the rules of the art and the recommendations of the quality controller.

6. Supply of equipment and installation of mechanical power supply systems:

The equipment of the mechanical feeding system was received on October 24, 2024 at the headquarters of the NGO CAV. These consisted of 10 stainless steel pipes, 10 stainless steel triangles, 1 stainless steel cylinder, 1 head, 1 frame and 1 spillway. This equipment or human-powered pump of the INDIA brand was installed on October 24, 2024 in the presence of the technical team of the NGO CAV including its Coordinator.

7. Technical and provisional reception of works:

The provisional technical reception of the work took place on November 1, 2024from 3 p.m. to 5 p.m. in the presence of local authorities, the beneficiary community, and the Water Committee. The GOOD LUCK company took part in the technical and provisional reception ceremonies.

In turn, the project team, local authorities and the Quality Control Officer of the works took the floor to provide advice to the populations for the proper use and management of the works carried out. The populations through the local authorities and the village development committee expressed their thanks to the COCHRAN Family for its financial contribution.

Several testimonies, especially those of women, were reported on the problems of access to water that they had before having a drinking water point today and in all seasons. They expressed to the NGO CAV and the COCHRAN Family their gratitude and reassured them that they will correctly use the facilities made available to them.

8. Coordination and monitoring of project activities.

Follow-ups were carried out by the project team. This team is composed of the Coordinator and the NGO. Monitoring tours of the drilling work were organized during the geophysical studies, drilling work, water pumping, during the construction of the superstructure. Telephone, email and Whatsapp contacts were exchanged between the project team, the company and the person responsible for technical monitoring of the project.

 

II - FINAL FINANCIAL REPORT OF THE SAGBADAÏ DRILLING PROJECT

INTRODUCTION

As part of the implementation of the project “ Improveaccess to water for the communities of Sagbadai in the prefecture of Tchaoudjo”, the NGO CAV mobilized a significant grant from the COCHRAN Family through GlobalGiving .

This report is the final financial assessment of all activities carried out within the framework of the implementation of this project in August 2024. It includes:

-          Funding received;

-          The bank journal of the NGO CAV and;

-          Budget execution.

1 - FINANCING RECEIVED 

The total amount of the grant is 8,415,052 CFA francs, or US$ 14,484   (1 US$ = 581 CFA francs). This grant is distributed as follows:

  • Human-powered drilling in Sagbadai in the Tchaoudjo prefecture at a cost of 7,100,000 CFA francs, or 12,220 $ US .
  • The operating costs for the NGO CAV amount to 1,315,052 CFA francs, or US$ 2,263 .

2 - THE BANK JOURNAL 

The total amount of expenditure incurred amounts to 8,415,052 CFA francs , or 14,484 US US.  dollars.of which :

  • The cost of financing the drilling is 7,100,000 CFA francs, or US$ 12,220;
  • The operating costs of the NGO CAV amount to 1,315,052 CFA francs, or 2,263 US dollars.

3 - BUDGET EXECUTION

The overall project completion rate is 100%.

For the NGO CAV, the Administrative and Financial Manager

KPEGOUNI Adjanakou

The Coordinator

GBELE-GUEWE Djobo Ousmane

Receipt of equipment on 10/24/2024 at NGO CAV
Receipt of equipment on 10/24/2024 at NGO CAV
Installation of the human-powered pump on 10/24/20
Installation of the human-powered pump on 10/24/20
View of the drilling on November 1, 2024 for its t
View of the drilling on November 1, 2024 for its t
Technical and provisional reception
Technical and provisional reception

Attachments: Share on Twitter Share on Facebook

Sep 29, 2024
MID - TERM REPORT OF THE DRILLING PROJECT OF SAGBADAI

By GBELE-GUEWE Djobo Ousmane | Coordinator

About Project Reports

Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.

Sign up for updates

Organization Information

Club des Amis du Village

Location: SOKODE, REGION CENTRALE / TOGO - Togo
Website:
Facebook: Facebook Page
X / Twitter: Profile
Project Leader:
Djobo GBELE-GUEWE
SOKODE , REGION CENTRALE / TOGO Togo

Funded Project!

Combined with other sources of funding, this project raised enough money to fund the outlined activities and is no longer accepting donations.
   

Still want to help?

Support another project run by Club des Amis du Village that needs your help, such as:

Find a Project

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence

Snorkeler
Our
Impact

Woman Holding a Gift Card
Give
Gift Cards

Young Girl with a Bicycle
GlobalGiving
Guarantee

Get incredible stories, promotions, and matching offers in your inbox

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.