Project Report
| Oct 30, 2015
Help Us To Complete The New Wells.
By Matthew Aidoo | Projects Coordinator
Work has been ongoing to ensure that the new Wells started are completed. In the last three months we have been working hard to achieve this. However lack of funds is making this very impossible. Work on the four (4) ongoing new Wells has far been advanced and almost completed. The concrete lining on all the four Wells has been done and what we need now is the hand pumps, which are urgently needed to complete the Wells for the target people to have access to clean water. People in the four (4) project communities including Esi Gyenfuaa (not real name) with her five children are eager to see the Wells completed.
We are still appealing to our cherish donors, friends and family to help us purchase four (4) Hand Pumps to complete the four outstanding Wells before December 2015 so that the over 1000 targeted people in these communities can have access to clean water before the dry season sets in from December.
Jul 31, 2015
Pumps Are Needed To Complete New Wells.
By Matthew Aidoo | Projects Coordinator
![TCWP-RP (11)]()
TCWP-RP (11)
Though donations to our project have not been forthcoming, we have not relented in our ongoing project aimed at providing clean water to our targeted people. In the last three months we have been working hard with the cooperation of the project communities to complete the work on the ongoing outstanding Four (4) Wells. All the concrete lining and the aprons on the Wells has been completed and what we need now is the Hand Pumps to help us complete the Wells for the four (4) communities to benefit.
We are therefore still appealing for donations from our cherish donors, friends and family to help us purchase four (4) Hand Pumps to complete the four outstanding Wells, which will benefit about 1000 people with clean water.
Description of pictures attached:
- TCWP-RP (11) Excavation work completed on the new Well.
- TCWP-RP (12) Concrete lining completed on the new Well.
- TCWP-RP (13) Apron on the new Well completed.
- TCWP-RP (14) The new Well is being covered and ready to be fitted with a hand pump.
![TCWP-RP (12)]()
TCWP-RP (12)
![TCWP-RP (13)]()
TCWP-RP (13)
![TCWP-RP (14)]()
TCWP-RP (14)
Apr 28, 2015
The Thirteenth Well Completed.
By Matthew Aidoo | Projects Coordinator
![- TCWP-RP (9)]()
- TCWP-RP (9)
Between November to April every year access to potable water is always a problem in our part of the world. Many households have to depend on unwholesome water for domestic purposes. For that matter, the Twansuokodu community was overwhelmed with joy to see the thirteenth well completed in their community. The completion of the Well was made possible with donations received recently and the community support. A hand pump was purchased and installed to complete the Well.
Many of the children including Manfred Gyesi and Joana Boateng( not real name) aged 13 & 15 years old from Twoansuokodu community are so happy because of the completed Well, from which they can easily access clean water that will benefit the entire community of about 250 people for all their chores. With this they will be healthy and prompt at school. We need water pumps to complete the almost completed outstanding Wells in the shortest possible time.
We are therefore still appealing for donations from our cherish donors, friends and family to help us completed the four outstanding Wells.
Description of pictures attached:
- TCWP-RP (9) Manfred helping Joana to carry water drown from the Thirteenth Well in the Twoansuokodu community.
- TCWP-RP (10) Joana smiling home with water just drown from the new Well.
![- TCWP-RP (10)]()
- TCWP-RP (10)